VEOLIA Trivalandes (western France)


Rules/Standards: APSAD

Assignment: Preliminary design

Find out more about our assignment
  • Definition of building fire detection equipment
  • Definition and design of fire control equipment
  • Definition of the Fire Safety System (FSS)
  • Definition and design of the fire pump room and water storage tank
  • Preparation of the process flow diagrams (PFDs) and associated diagrams
  • Pre-structural design calculations

SUEZ R&V ASTRIA – Bègles


Rules/Standards: APSAD

Assignment: Technical assistance on fire protection/detection work

Find out more about our assignment
  • Management/Coordination/Scheduling
  • Basic preliminary design study
  • Preparation of tender documentation
  • Call for tenders
  • Assistance in contractor selection process
  • Approval of contractors’ working drawings
  • Follow-up of execution work
  • Assistance with acceptance operations

SUEZ – Sainte-Suzanne – LA REUNION


Rules/Standards: APSAD / ICPE

Assignment: Technical assistance on fire protection work

Find out more about our assignment
  • Detailed engineering design
  • Writing of the technical specifications for the fire detection/protection work
  • Tender documentation
  • Assistance with contractor selection process
  • Approval of construction documents
  • Assistance during the works phase
  • Assistance with acceptance operations

S.I.A.A.P. SEINE AMONT Valenton


Rules/Standards: APSAD and ICPE

Assignment: Consultancy work

Find out more about our assignment
Fire vulnerability study of the Seine Amont site (S.E. of Paris).
  • Technical and regulatory inventory of the existing fire safety systems.
  • Study of the sites’ vulnerability in relation to fire.
  • Definition of a functional and technical master plan for fire protection at the Site.
  • Creation of a technical design and construction repository for fire safety installations with reference to the master plan.
  • Fire safety systems improvement plan.

SYCTOM ROMAINVILLE / VALORAM


Rules/Standards: APSAD

Assignment: Client assistance and amendment to sign off as-built documents.

Find out more about our assignment
The objective was to equip the installations of the new waste receiving, sorting and conditioning unit and the building housing the installations with adequate, compliant fire safety systems (detection, prevention, evacuation and firefighting equipment).
  • Preliminary design.
  • Document approval.
  • Assistance for the planning and supervision of works.
  • Assistance with acceptance operations.

GRENOBLE-ALPES METROPOLE


Rules/Standards:

Assignment: Feasibility study.

Find out more about our assignment
Feasibility study to help in the choice of fire detection and/or protection solutions at the waste sorting centre and the incinerator receiving zone of Grenoble-Alpes Metropole (S.E. France).
  • Visual audit of the existing facilities.
  • Document analysis and regulatory review.
  • Basic design of the various conceivable technical solutions.
  • Budget estimate of the work to be done.
  • Preparation of a technical/economic comparison.
  • Process flow diagrams of the planned solutions.
  • Writing of an audit and feasibility study report.

BIL TA GARBI – TMB CANOPIA BAYONNE: URBASER ENVIRONNEMENT


Rules/Standards: APSAD

Assignment: Conceptual definition/Diagnostic of safety systems

Find out more about our assignment
Conceptual definition of partitioning. Fire safety system diagnostics. Phase 1: Mapping and analysis of existing devices, focusing mainly on:
  • Existing construction set-ups.
  • Current fire detection and extinguishing systems.
Phase 2: Vulnerability study, to include the interpretation and assessment of the set-ups implemented at the organisation’s units. Phase 3: Master plan which will propose, rank and cost any extra measures to limit the risks.

URBASER – SEPOC VALORTEGIA Bayonne


Rules/Standards:

Assignment: Project Management.

Find out more about our assignment
Design phase:
  • Basic preliminary and detailed engineering design.
  • Preparation of the project budget.
  • Assistance with contractor selection process.
  • Writing of the particular technical specifications for the fire detection/protection work package.
  • Tender documentation.
Construction phase:
  • Approval of construction documents.
  • Coordination of pre-commissioning operations.
  • Assistance with acceptance operations.
  • Installation supervision.

SIDEPAQ – UVE de Briec de L’odet


Rules/Standards:

Assignment: Project Management

Find out more about our assignment
Design phase:
  • Preliminary design.
  • Production of drawings and associated process flow diagrams.
  • Detail design.
  • Writing of the particular technical specifications.
  • Tender documentation.
  • Assistance with contractor selection process.
Construction phase:
  • Document approval.
  • Planning and supervision of contractors’ work.
  • Assistance with acceptance operations.